I
Improve Capacity Of The 110kV Dak Ha- Kon Tum Transmission Line
Improve Capacity Of The 110kV Dak Ha- Kon Tum Transmission Line
| Thông tin dự án | |
|---|---|
| Project | Improve Capacity Of The 110kV Dak Ha- Kon Tum Transmission Line |
| Investor | Central Rural Electricity Project Management Board |
| Project scale | 110kV line |
| Year | 2019 |
| Location | Kon Tum Province |
504 Power implemented the project of Improving Capacity Of The 110kV Dak Ha line – 220kV Kon Tum Substation in 2019 for the Investor – Central Rural Electricity Project Management Board with the following scope of work:
- Construction survey consulting
- Preparing construction investment feasibility study report, making environmental profile
- Designing construction works