Project | 110kV Bao Ninh Substation and Connection |
Investor | Central Rural Electricity Project Management Board (CREB) |
Project scale | 110kV line and substation |
Year | 2016 |
Location | Quang Binh Province |
From 2016 to 2020, 504 Power implemented the "Bao Ninh 110kV Substation and Connection" project for the Central Rural Electricity Project Management Board (CREB) in Quang Binh province with the following scope of work:
- Consulting and surveying construction.
- Preparing the construction investment feasibility study report.
- Designing construction drawings.