| Thông tin dự án | |
|---|---|
| Project | Connecting 110kV after 220kV Lao Bao substation |
| Investor | Central Network Project Management Unit |
| Project scale | 110kV line |
| Year | 2017-2020 |
| Location | Quang Tri Province |
From 2017 to 2020, 504 Power implemented the "Connecting 110kV after 220kV Lao Bao substation" project in Quang Tri province for the Investor - Central Power Grid Project Management Board with the scope of work including:
- Construction consulting and construction survey
- Preparing construction investment feasibility study report
- Making estimates in the design.