Consulting on design of electrical works
110kV Tay Son Transformer Station and Connection
In 2018, 504 Power implemented the 110kV Tay Son Transformer Station and Connection project for the Central Rural Electricity Project Management Board in Quang Ngai province with the following scope of work:
- Construction survey consulting
- Prepare construction investment feasibility study report
- Making environmental profile
- Making design and construction works
110kV Bao Ninh substation and connection
From 2016 to 2020, 504 Power implemented the 110kV Bao Ninh Substation and Connection project for the Central Rural Electricity Project Management Board in Quang Binh province with the following scope of work:
- Consulting and surveying construction.
- Preparing the construction investment feasibility study report.
- Designing construction drawings.